DMS completed the installation of a 1.6 MW containerized landfill gas to energy project spanning Ontario and New Brunswick. Major plant equipment included a containerized generator set, a remote radiator, and a packaged landfill gas conditioning skid. DMS prefabricated the gas conditioning skid at our Ontario facility before shipping it to the project site, where our team carried out equipment rigging and installation, process piping, and miscellaneous steel fabrication and erection.
Our scope included a range of process piping systems: landfill gas, various hydronic systems, urea, compressed air, and exhaust breeching. The landfill gas piping and equipment were installed in accordance with all local regulations, including CSA B149.6, ensuring a safe, reliable, and code-compliant energy facility.